Contractors - Pre-lien notice must be included in your contract.
Subcontractors - must serve the property owner personally, or by certified mail, with pre-lien
notice within 45 days after subcontractor's first item of contribution.
Owners - all are entitled to pre-lien notice.
Exceptions - pre-lien notice is unnecessary when the contractor is managed by the same person
that manages the owner.